Centerra Industrial Building #7

Our Portfolio
Project Description

This project consists of a roughly 123,306 SF core and shell, concrete, tilt-up, warehouse building.

There is no tenant finish within the scope, only the new construction of the shell of the warehouse. This project had a relatively tight schedule that ended up finishing at 201 days.

An aerial shot of a commercial building on the portfolio page for an automotive contractor that built a les schwab tire center in fort morgan, co.
An under construction image of the inside of a large commercial garage that was part of a Les Schwab Tire Center built by an automotive contractor in Colorado.
Project Information
Location
Loveland, CO
Area
Front Range
Building Size
123,306 SF
Duration
6.6 Months
Building Type
Industrial | Warehouse
Construction Type
Tilt-Up, New Construction
Delivery Method
Cost-Plus
Owner
McWhinney
Architect
Ware Malcomb
Strategy
The biggest hurdle in this project is the tight schedule. Additionally, it had been a relatively snowy spring here in Colorado so the snow and cold also added slightly to any delay in schedule. The original schedule was 187 days and our team finished at 201 days, even with the intense weather delays.